Mega projectPartially open
Riyadh Metro
Riyadh · Riyadh Region · Announced 2013 · Target Fully open 2025
Developer / Owner
Royal Commission for Riyadh City
Project manager
WSP / Louis Berger
Consultants
Zaha Hadid Architects, Snøhetta, Systra
Location
24.66°N, 46.78°E
Cost tracker
$25bn
Network fully operational since January 2025 — budget essentially deployed
$25bn
reported cost
100% of the reported cost
Figures as of December 2024 · Royal Commission for Riyadh City / Zawya
About the project
A six-line, 176 km driverless metro network with 85 stations, delivered by three international consortia and now progressively open to passengers.
Project features
- 6 lines, 176 km, 85 stations
- Fully automated driverless trains
- KAFD station by Zaha Hadid Architects
- Integrated with a 3,000-bus rapid transit network
Tenders & awards
Operations & maintenance — network wide
AwardedPackage: O&M
Won by: Capital Metro Company (RATP / SAPTCO)
Contractors on site
BACS Consortium (Bechtel)ArRiyadh New Mobility (Ansaldo)FAST Consortium (FCC)